Parking Lot B

Vike Construction has been awarded the civil works for Parking Lot B. They are bringing their equipment up on May 28 and will begin work either that day or the next and it is scheduled to be completed by June 18.

This work is in preparation for the Washroom/Shower building which will be going out to bid at the end of the month.

John Sorenson and his team from WWK Engineering Limited Partnership will be managing this project.